PE-10 Emergency Shutoff
Review PE-10
1. Set its parameters
No parameters to set for PE-10.
2. Record its status
a.Provide the capability of shutting off power to [Assignment: organization-defined system or individual system components] in emergency situations;
b.Place emergency shutoff switches or devices in [Assignment: organization-defined location] to facilitate access for authorized personnel; and
c.Protect emergency power shutoff capability from unauthorized activation.
Discussion
Emergency power shutoff primarily applies to organizational facilities that contain concentrations of system resources, including data centers, mainframe computer rooms, server rooms, and areas with computer-controlled machinery.
Enhancements
No Enhancements match this Baseline.
ISO/IEC 27001:2022 Crosswalk